Railways Achieves 6.59-km Tunnel Breakthrough on Rishikesh–Karnaprayag Line in Uttarakhand

56 minutes ago

2

0

Yugcharan News / 28-11-2026

New Delhi: Indian Railways and Rail Vikas Nigam Limited (RVNL) have achieved the main breakthrough of Tunnel-14, a 6.59-kilometre tunnel on the Rishikesh–Karnaprayag rail project in Rudraprayag district of Uttarakhand, the Ministry of Railways said in a statement issued on Friday, November 27. The two excavated sections of the tunnel have now been joined: 4.7 km from Portal-1 at Sumerpur and 1.79 km from Portal-2 at Marora, according to the Press Information Bureau and Deccan Herald.

How the two ends were joined

The Indian Express, citing RVNL, said the work was carried out in difficult geological conditions, including loose soil beneath inhabited areas, unstable slopes and the need for controlled blasting to reduce risk to nearby settlements. At Portal-1, engineers excavated a 110-metre stretch of the triple-track tunnel through loose soil, with only 20 to 30 metres of soil and rock above it, the ministry and RVNL said. Specialised methods, including pre-excavation and multi-drifting, were used, according to the official statement.

At Portal-2, near Marora, the slope was secured with micropiles 30 to 35 metres deep, rock bolts 15 to 20 metres long, and consolidation grouting, the statement said. These measures allowed the main tunnel drive to start in March 2024, after ground settlement at Marora and issues related to land and home acquisition had been addressed. About 100 metres of mechanical excavation was carried out at this portal. Controlled blasting near both portals was restricted to daytime hours to protect nearby settlements, the ministry said. Specialised ventilation systems were used during the 4.7 km drive from Portal-1 to supply fresh air and regulate temperature inside the tunnel.

A largely underground Himalayan line

The Rishikesh–Karnaprayag new broad-gauge line is a 125-km project being built by RVNL under the Ministry of Railways, Deccan Herald reported. The Indian Express said the project was sanctioned in the Union Budget of 2010-11 and passes through Dehradun, Tehri Garhwal, Pauri Garhwal, Rudraprayag and Chamoli districts. It is meant to connect religious destinations such as Devprayag and Karnaprayag with Rishikesh and, through the existing network, the national capital.

Deccan Herald reported that 80 to 85 per cent of the alignment runs through tunnels. The project includes 16 main tunnels spanning about 104 km and 12 escape tunnels covering around 98 km, along with multiple bridges, according to both The Indian Express and Deccan Herald. The official statement described the project as a strategically important initiative to improve rail connectivity in the hill regions of Uttarakhand.

Cost, progress and target date

The project is currently estimated to cost about ₹37,119 crore, The Indian Express and Deccan Herald reported. RVNL Chairman and Managing Director Saleem Ahmad has said the project has achieved 79 per cent overall progress, with about 97 per cent of the tunnel excavation completed, and that it is targeted for completion by December 2029, according to The Indian Express. Deccan Herald repeated the same progress figures and completion target.

Once the line is operational, travel time between Rishikesh and Karnaprayag is expected to fall from six to seven hours by road to around two to two-and-a-half hours by train, Deccan Herald reported. The newspapers said the line is also expected to improve access for pilgrims and tourists travelling towards Char Dham destinations, support local economies and strengthen connectivity in the border region. These are the stated aims of the project; the travel-time figure is an estimate reported by Deccan Herald and will be tested only after the line opens.

The official statement said the project would provide better connectivity to the hill regions, facilitate travel for pilgrims and tourists, and support regional development by improving access to important destinations in the state. Deccan Herald named Srinagar and Rudraprayag among the towns the line is intended to serve, along with Devprayag and Karnaprayag, and said it would link Yog Nagari Rishikesh with Karnaprayag.

What the breakthrough does, and does not, mean

A tunnel breakthrough means the two excavation faces have met, so the main bore of Tunnel-14 is now continuous. It does not mean the tunnel is ready for trains. Lining, track, signalling, ventilation and safety systems still have to be completed, and the rest of the 125-km line, including other tunnels and bridges, remains under construction. The official releases do not give a separate opening date for Tunnel-14, only the December 2029 target for the project as a whole.

The ministry's statement and the two newspaper reports, which rely on it and on RVNL, do not specify how many workers were involved in Friday's breakthrough, or whether any further tunnels still await a similar meeting of faces. The official releases do not break down how much of the remaining excavation, if any, is still to be done after Friday's breakthrough.

The Rishikesh–Karnaprayag line has been under construction for several years in steep Himalayan terrain. Friday's breakthrough is one of the larger remaining underground sections to be joined. Passengers will be able to use the new route only after the project is completed and commercial services are notified by the Railways.

Photo: Yog Nagari Rishikesh railway station, by Ravi Dwivedi, Wikimedia Commons, CC BY-SA 4.0. The station is the existing railhead at Rishikesh, from which the new line is planned to run; the picture does not show Tunnel-14.

Click here to Read More
Previous Article
दिल्ली की हवा 'खराब' श्रेणी में, रविवार को 'बहुत खराब' होने का अनुमान; मथुरा रोड पर एक्यूआई 333
Next Article
आरबीआई ने बैंकों की न्यूनतम दैनिक सीआरआर सीमा 99% से घटाकर 90% की, 40,000 करोड़ रुपये से ज्यादा खुलने की उम्मीद

Related National Updates:

Are you sure? You want to delete this comment..! Remove Cancel

Comments (0)

    Leave a comment